HIGHLIGHTS
Second batch of assays received for 2025 drilling at Vail Road Gold Deposit,
including best down hole intercepts of:
o VR-25-75 – 5.0m at 3.90 g/t Au from 56.0m
including: 1.0m at 17.20 g/t Au from 57.0m
o VR-25-77 – 2.33m at 24.81 g/t Au from 51.92m
including: 1.0m at 57.50 g/t Au from 53.25m
o VR-25-80 – 3.40m at 1.70 g/t Au from 4.7m
including: 1.2m at 3.13 g/t Au from 6.1m
o VR-25-82 – 2.03m at 3.35 g/t Au from 23.02m
including: 0.8m at 8.13 g/t Au from 24.25m
New results follow on from previously released first assay batch received in
January, 1
with down hole intercepts including:
o VR-25-76 – 6.27m at 33.74 g/t Au from 54.43m
including: 2.57m at 70.66 g/t Au from 57.26m
o VR-25-70 – 0.5m at 25.9 g/t Au from 100.20m
o VR-25-71 – 1.0m at 17.42 g/t Au from 61.20m
including: 0.5m at 33.6 g/t Au from 61.70m
o VR-25-72 – 0.6m at 11.30 g/t Au from 66.3m
These high-grade gold results will be incorporated in an updated Mineral
Resource Estimate to be reported under the JORC code
Shallow intercepts demonstrate continuity of grade to surface in parts of the
vein system.
Albright Metals Limited (“Albright Metals” or “the Company”) provides results from
the second batch of diamond core drill samples from the Vail Road Gold Deposit
at the Golden Pike Project. Results reported are from a further nine of the total 15
holes drilled during November and December 2025.2
Results from four drill holes
were previously reported in January 2026.1
In total 1,020.5 metres of HQ core were
drilled at the Vail Road Gold Deposit. Two holes are still pending sampling and
assay, with intervals for sampling identified during update of the geological model.
1
ASX announcement 28 January 2026 ‘High-Grade Gold Results for Golden Pike Project’
2
ASX announcement 22 December 2025 ‘Gold and Antimony Drilling Program Update’
ASX: ABR | albrightmetals.com 2
CEO, Greg Hill comments, “This second batch of assays further confirms the
exceptional high-grade nature of the Vail Road Gold Deposit. The results support
Albright Metals’ plans for rapid progression to a Mineral Resource Estimate
reported under the JORC code and mine development studies.”
These recently received assay results for the Vail Road Gold Deposit continue to
demonstrate the high-grade present in the three main zones, being the Main
Zone, the Middle Zone and the Parallel Zone. The best down hole intercept in this
batch of results was hole VR-25-77 that intercepted the main zone for 2.33m at
24.81 g/t Au from 51.92m, including 1.0m at 57.50 g/t Au from 53.25m. Results from
the successful initial drill program at the Vail Road gold deposit by Albright Metals
confirm the historical grade tenors reported for the deposit.
Results are now returned for all samples submitted. The drill program was staffed
by a team of in-country geologists and drillers. Review of core and assay results
will be consolidated for additional sampling and assaying in the coming month to
resolve further potential for mineralisation in the 2025 drill holes.
Vail Road Diamond Drilling
The drilling by Albright Metals during 2025 at the Vail Road Gold Deposit was
designed to:
Infill portions of the Parallel Zone to test continuity.
Replicate some historical holes as quality assurance for a pending mineral
resource estimation to be reported under the JORC code.
Infill the shallowest portions of the Main Zone in preparation for future works
mine planning.
Drill oriented drill core to collect structural data on the vein contacts and any
confining structures.
Acquire sufficient core sample for metallurgical recovery and processing
test work.
Table 1 summarises all returned gold results greater than 0.5 g/t attributable to the
same vein based on logging, with these intercepts highlighted on the collar plan
in Figure 1. Location details for all holes drilled during 2025, with assay return
status, are provided in Appendix 1.
Table 1: Vail Road 2025 Drilling Downhole Intercept Results greater than 0.5 g/t Au
Hole ID From (m) To (m)
Interval
(m)
Au g/t
Au
Gram
Metre
Zone
VR-25-73 NSI
VR-25-74 20.19 20.94 0.75 0.69 0.52 Parallel Zone
VR-25-74 74.35 77.3 2.95 1.85 5.47 Middle Zone
VR-25-75 56 61 5.0 3.90 19.50 Middle Zone
including 57 58 1.0 17.20 17.20 Middle Zone
VR-25-77 44.4 45.17 0.77 9.40 7.24 Main Zone
ASX: ABR | albrightmetals.com 3
Hole ID From (m) To (m)
Interval
(m)
Au g/t
Au
Gram
Metre
Zone
VR-25-77 51.92 54.25 2.33 24.81 57.80 Main Zone
including 53.25 54.25 1.0 57.50 57.80 Main Zone
VR-25-78 Exploration hole – sampling and assays pending
VR-25-79 NSI
VR-25-80 4.7 8.1 3.4 1.70 5.79 Main Zone
including 6.1 7.3 1.2 3.13 3.76 Main Zone
VR-25-80 4.7 8.1 3.4 1.70 5.79 Main Zone
VR-25-81 Sampling of Main Zone to be completed – sampling and assays pending
VR-25-82 23.02 25.05 2.03 3.35 6.79 Main Zone
including 24.25 25.05 0.8 8.13 6.50 Main Zone
VR-25-83 14.3 14.9 0.6 0.63 0.38 Main Zone
VR-25-83 31.2 32 0.8 0.92 0.74 Main Zone
VR-25-84 NSI
Previously Reported:
VR-25-70 19.4 20 0.6 1.35 0.81 Parallel Zone Hangingwall
VR-25-70 100.2 100.7 0.5 25.9 12.95 Parallel Zone Hangingwall
VR-25-70 116.33 117.1 0.77 4.23 3.26 Parallel Zone
VR-25-71 27.25 27.85 0.6 1.5 0.9 Parallel Zone Hangingwall
VR-25-71 61.2 62.2 1.0 17.42 17.42 Parallel Zone
including 61.7 62.2 0.5 33.6 16.8 Parallel Zone
VR-25-72 66.3 66.9 0.6 11.3 6.78 Parallel Zone
VR-25-76 54.43 60.7 6.27 33.74 211.58 Middle Zone
including 57.26 59.83 2.57 70.66 181.6 Middle Zone
NSI: No significant intercept
Multi-element results have been returned for the initial batch of samples
submitted for the Vail Road drilling. There are no economic quantities of base
metals or silver in the results. The multi-element data will be used to assist with
characterisation of the mineralised rock for processing studies and waste rock for
mine studies and to confirm lithological domaining in the geology model.
ASX: ABR | albrightmetals.com 4
Figure 1: Collar plan for 2025 Vail Road gold deposit drilling with received intercepts1
The Main, Middle and Parallel zones are labelled on Figure 1, projected to surface.
The Parallel zone and Main zones extend to surface for at least a portion of their
strike. A cross section in the middle of the deposit with the outstanding intercept
in the Main Zone in hole VR-25-77 is presented in Figure 2. Results previously
released earlier in 2026 are shown in addition to these new results. Historical drill
results from previous operators at the Project are shown on the section.3
3
ASX announcement 21 May 2025 ‘Acquisition of Advanced High-Grade Gold Project’
ASX: ABR | albrightmetals.com 5
Figure 2: Cross Section B – B’ – VR-25-77 Significant Intercept
Next steps
Additional sampling of the Vail Road Gold Deposit holes drilled during 2025 will be
undertaken in the coming weeks. These samples will test zones where there is
significant structure or alteration, or where the intervals coincide with expected
mineralised horizons. The additional assay information will be used for the
upcoming geological modelling and mineral resource estimation for reporting
under the JORC code.
Structural data analysis of the Vail Road Gold Deposit is ongoing and further
specific gravity data will be collected on historical core from it.
ASX: ABR | albrightmetals.com 6
Figure 3: Golden Pike Project Location and Prospect Map
For further information, please contact:
Greg Hill
Chief Executive Officer
+61 8 9321 0001
albrightmetals.com
ASX: ABR | albrightmetals.com 7
This announcement has been produced in accordance with the Company's
published continuous disclosure policy and has been approved by the Board.
ASX: ABR | albrightmetals.com 8
ABOUT ALBRIGHT METALS
Albright Metals’ current projects are located in Canada and Western Australia, both Tier
One mining and exploration jurisdictions.
Albright Metals has executed an agreement with Globex Mining Enterprises Inc. (GMX-
TSX, GLBXF-OTCQX, G1MN-FSE) to acquire the Golden Pike Gold and Antimony Project in
New Brunswick, Canada.4
The project covers approximately 3,292ha of contiguous mining
claims which includes the Vail Road high-grade gold deposit classified under NI 43-101,5
and the exploration-stage Bond Road antimony prospect. The Golden Pike Project is in an
area that is close to road, rail, port and grid power infrastructure. Southern New Brunswick
is on the Canadian east coast, adjacent to Maine, USA. It enjoys a mild maritime climate,
allowing year round exploration activities. The province has a mature mining services
industry and has historically produced antimony and gold from multiple mines.
Albright Metals has a substantial $7M manganese joint venture on licences in the Bryah
Basin with ASX listed OM Holdings Limited (ASX: OMH), with OMH having already spent
over $4.5 million to earn-in to the Manganese Rights of the project.
Albright Metals holds a suite of mineral rights, including copper, nickel and gold, over the
Gabanintha project, near Meekatharra, 6
which has a JORC 2012 Mineral Resource for Cu,
Ni, Co and additional structural gold potential.
Albright Metals was formerly known as Bryah Resources, trading under the ASX code BYH.
COMPLIANCE STATEMENTS
The information in this announcement that relates to exploration results is based on
information compiled by Ms Gemma Lee, who is a Member of the Australian Institute of
Geoscientists (AIG) and is Principal Geologist for Albright Metals Limited. Ms Lee has
sufficient experience which is relevant to the style of mineralisation and type of deposit
under consideration and to the activity which she is undertaking to qualify as a
Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting
of Exploration Results, Mineral Resources and Ore Reserves’. Ms Lee consents to the
inclusion in this announcement of the matters based on her information in the form and
context in which it appears.
Where the Company refers to Exploration Results in this announcement (referencing
previous releases made to the ASX), the Company is not aware of any new information or
data that materially affects the information included in the relevant market
announcements.
FORWARD LOOKING STATEMENTS
This announcement may contain certain “forward-looking statements” which may not
have been based solely on historical facts, but rather may be based on the Company’s
current expectations about future events and results. Where the Company expresses or
4
See ASX announcement 11 July 2025 ‘Option Exercised to Acquire High-Grade Canadian Gold Project’
5
See ASX announcement 21 May 2025 ‘Acquisition of Advanced High-Grade Gold Project’
6
See ASX announcement 25 May 2022 ’36 Million Tonne Nickel-Copper-Cobalt Mineral Resource at
Gabanintha’
ASX: ABR | albrightmetals.com 9
implies an expectation or belief as to future events or results, such expectation or belief is
expressed in good faith and believed to have a reasonable basis. However, forward looking
statements are subject to risks, uncertainties, assumptions and other factors which could
cause actual results to differ materially from future results expressed, projected or implied
by such forward-looking statements. Readers should not place undue reliance on forward
looking information. The Company does not undertake any obligation to release publicly
any revisions to any “forward looking statement” to reflect events or circumstances after
the date of this report, or to reflect the occurrence of unanticipated events, except as may
be required under applicable securities laws.
ASX: ABR | albrightmetals.com 10
APPENDIX 1
Collar Table – Vail Road Gold Deposit – Golden Pike Project
Co-ordinate System: NAD83 Zone 20
Hole ID
Depth
(m)
East North RL Dip Azimuth
Results
Returned
VR-25-70 125 273,244 5,061,359 153 - 43 120
Au and multi-
element
VR-25-71 80 273,321 5,061,351 159 - 44 117
Au and multi-
element
VR-25-72 77 273,348 5,061,375 162 - 44 117
Au and multi-
element
VR-25-73 66.5 273,281 5,061,282 154 - 44 140 Au Only
VR-25-74 98 273,281 5,061,283 154 - 44 115 Au Only
VR-25-75 65 273,364 5,061,266 157 - 90 0 Au Only
VR-25-76 74 273,327 5,061,270 155 - 74 145
Au and multi-
element
VR-25-77 65 273,403 5,061,279 160 - 53 117 Au Only
VR-25-78 182 273,390 5,061,196 154 - 48 140 Pending
VR-25-79 29 273,392 5,061,216 156 - 43 117 Au Only
VR-25-80 38 273,390 5,061,231 156 - 43 117 Au Only
VR-25-81 26 273,403 5,061,225 157 - 44 117 Pending
VR-25-82 30 273,405 5,061,240 159 - 43 117 Au Only
VR-25-83 41 273,403 5,061,241 159 - 66 117 Au Only
VR-25-84 26 273,422 5,061,255 160 - 43 117 Au Only
ASX: ABR | albrightmetals.com 11
APPENDIX 2: JORC Code, 2012 Edition – Table 1 Exploration Results
Section 1 Sampling Techniques and Data
Criteria JORC Code explanation Commentary
Sampling
techniques
Nature and quality of
sampling (e.g. cut channels,
random chips, or specific
specialised industry standard
measurement tools
appropriate to the minerals
under investigation, such as
down hole gamma sondes, or
handheld XRF instruments,
etc). These examples should
not be taken as limiting the
broad meaning of sampling.
Include reference to
measures taken to ensure
sample representivity and the
appropriate calibration of any
measurement tools or
systems used.
Aspects of the determination
of mineralisation that are
Material to the Public Report.
In cases where ‘industry
standard’ work has been
done this would be relatively
simple (e.g. ‘reverse
circulation drilling was used
to obtain 1m samples from
which 3 kg was pulverised to
produce a 30 g charge for fire
assay’). In other cases, more
explanation may be required,
such as where there is coarse
gold that has inherent
sampling problems. Unusual
commodities or
mineralisation types (e.g.
submarine nodules) may
warrant disclosure of detailed
information.
Sample results in this release
are for HQ diameter core
samples submitted as cut
quarter core samples.
Gold results for the initial
batch were determined by
30gram Fire Assay with Atomic
Absorption Spectrometry
(AAS) finish, with over
detection limit (5 g/t Au)
resolved by Gravimetric Fire
Assay. For this latest batch, ore
grade AAS finish on a 30gram
Fire Assay was employed with
an over-detection limit of 100
g/t Au, reducing the
requirement for reanalysis of
some results with Gravimetric
finish.
Down hole intercepts are
reported with true widths not
calculated, due to structural
data analysis and geological
model update being in
progress at the time of writing.
Coarse-crush splits were taken
every 15th
sample and the
second split also analysed by
the lab to evaluate the
representivity of lab splitting
for the initial batch; this work is
pending for this second batch
of results.
All results greater than 0.5 g/t
Au are reported as intercepts
where contiguous samples
represent the same
mineralised vein.
Sample weights ranged
between 800 grams and 2.5
kg, with sample length ranges
of 0.3 – 1.1m submitted for
assay.
ASX: ABR | albrightmetals.com 12
Criteria JORC Code explanation Commentary
Drilling
techniques
Drill type (e.g. core, reverse
circulation, open-hole
hammer, rotary air blast,
auger, Bangka, sonic, etc)
and details (e.g. core
diameter, triple or standard
tube, depth of diamond tails,
face-sampling bit or other
type, whether core is
oriented and if so, by what
method, etc).
Drilling results for this release
are HQ diamond core results.
HQ diameter produces
63.5mm diameter core.
Recovery was good, averaging
96.5% over all holes with
standard tube drilling. Good
recovery is due to lack of
weathering profile and
competent geology.
Core was oriented using an H
ACTIII tool. Orientation line
continuity was deemed good
through large portions of the
drilling where multiple
orientation marks aligned
through competent core with
less than 10 degrees deviation
between marks.
Drill sample
recovery
Method of recording and
assessing core and chip
sample recoveries and results
assessed.
Measures taken to
maximise sample recovery
and ensure representative
nature of the samples.
Whether a relationship exists
between sample recovery
and grade and whether
sample bias may have
occurred due to preferential
loss/gain of fine/coarse
material.
Drill core was accurately metre
marked and recovery recorded
for every run (standard runs at
3m lengths being 2x 1.5m
rods).
RQD was measured for the
core with values averaging
78%.
Field duplicates (second
quarter core) samples were
not submitted due to known
high nugget effect in the
deposit, however a second
coarse crush split was taken
every 15th
sample to evaluate
lab splitting. Results show high
repeatability.
There is no relationship
evident between sample
recovery and grade.
Logging Whether core and chip
samples have been
geologically and
geotechnically logged to a
level of detail to support
appropriate Mineral Resource
estimation, mining studies
and metallurgical studies.
All drilled metres (with
exception of casing that was
rock rolled – typically top 3.5m)
was logged for lithology,
veining, mineralisation,
alteration and structure,
representing greater than 95%
of total hole depths logged.
ASX: ABR | albrightmetals.com 13
Criteria JORC Code explanation Commentary
Whether logging is
qualitative or quantitative in
nature. Core (or costean,
channel, etc) photography.
The total length and
percentage of the relevant
intersections logged.
Geotechnical logging was
collected on all core.
Logging is both qualitative and
quantitative in nature.
All core is photographed.
Core is logged to a level of
detail to support Mineral
Resource estimation, mining
studies and metallurgical
studies.
Sub-sampling
techniques and
sample
preparation
If core, whether cut or sawn
and whether quarter, half or
all core taken.
If non-core, whether riffled,
tube sampled, rotary split, etc
and whether sampled wet or
dry.
For all sample types, the
nature, quality and
appropriateness of the
sample preparation
technique.
Quality control procedures
adopted for all sub-sampling
stages to maximise
representivity of samples.
Measures taken to ensure
that the sampling is
representative of the in-situ
material collected, including
for instance results for field
duplicate/second-half
sampling.
Whether sample sizes are
appropriate to the grain size
of the material being
sampled.
Core samples are quarter core
(twice cut) samples from HQ
diameter core. Quarter core
samples were submitted due
to the larger diameter holes
(compared to NQ) and to
ensure archive sample is
retained for future
metallurgical test work.
Quality control procedures
were performed at the
laboratory to ensure sub-
sampling techniques during
sample preparation are
representative, including client
requested second coarse-
crush splits every 15th
sample.
Sample preparation employed
by the lab includes drying,
weighing (weights reported),
coarse crush, split, pulverise
then sub-sampling the pulp
for fire assay. The lab
completed in-house coarse-
crush and pulp repeats to
ensure sample representivity.
Albright Metals included blank
samples in the submission to
test for grade smearing during
sample preparation with no
issues detected.
No field duplicates were
submitted during the program
to test ground variability,
however twins of historical
holes were included in the drill
plan to test ground variability
ASX: ABR | albrightmetals.com 14
Criteria JORC Code explanation Commentary
and repeatability of drill
results.
Sample sizes are considered
representative to the grain size
of the material being sampled.
Quality of assay
data and
laboratory tests
The nature, quality and
appropriateness of the
assaying and laboratory
procedures used and
whether the technique is
considered partial or total.
For geophysical tools,
spectrometers, handheld
XRF instruments, etc, the
parameters used in
determining the analysis
including instrument make
and model, reading times,
calibrations factors applied
and their derivation, etc.
Nature of quality control
procedures adopted (e.g.
standards, blanks, duplicates,
external laboratory checks)
and whether acceptable
levels of accuracy (i.e. lack of
bias) and precision have
been established.
All sample analyses for the
2025 drill core samples were
conducted by Activation
Laboratories Ltd. (Actlabs),
Ontario, a certified commercial
lab, following sample
preparation at the New
Brunswick, Fredericton facility.
Gold was analysed by Fire
Assay with an Atomic
Absorption finish (FA-AA), with
a maximum detection limit of
5 g/t Au. Samples that were
over detection limit were also
assayed with Fire Assay with
Gravimetric finish to resolve
the grade above the detection
limit of the FA-AAS method.
For the second batch, Fire
Assay was run with ore grade
AAS finish, to resolve up to 100
g/t Au and reduce
requirement for reanalysis
with Gravimetric Finish.
Multi-element analysis on the
first batch was completed with
a 4 Acid Digest with ICP AES or
MS finish for a suite of 48
elements.
Albright Metals submitted
standards (CRMs) at a
frequency of one CRM per
mineralised zone; blanks at a
frequency of one blank per
mineralised zone, and
requested additional coarse-
crush splits and analysis at a
frequency of 1 per 15 samples.
No issues with laboratory
analytical accuracy (CRMs),
smearing of gold across
ASX: ABR | albrightmetals.com 15
Criteria JORC Code explanation Commentary
samples (blanks) or sub-
splitting at the lab (second
coarse crush splits) has been
detected.
No umpire laboratory samples
have been submitted to date.
Verification of
sampling and
assaying
The verification of significant
intersections by either
independent or alternative
company personnel.
The use of twinned holes.
Documentation of primary
data, data entry procedures,
data verification, data
storage (physical and
electronic) protocols.
Discuss any adjustment to
assay data.
Significant intercepts by
Rockport Mining Corporation
(“Rockport”) in previous drill
campaigns have been checked
as part of the program by
drilling several holes in
proximity to existing holes.
This initial set of results for the
2025 drilling indicates the
historical drill results are
repeatable.
Albright Metals has conducted
an internal peer review of
results with other geological
staff.
Data collection procedures
were well defined during the
program processing with
validation and completeness
checks performed internally
and by the external database
managers. Data was collected
directly into digital files, then
stored in a secure location on
the cloud in an organised
directory for transfer to the
Company database
administrators for load.
No adjustments have been
made to assay data apart from
replacing below detection
limit values with half detection
limit.
Location of data
points
Accuracy and quality of
surveys used to locate drill
holes (collar and down-hole
surveys), trenches, mine
workings and other locations
used in Mineral Resource
estimation.
Diamond core holes were
pegged prior to drilling with
an RTK DGPS system, then the
collar surveyed again after the
hole was completed with RTK
DGPS.
The coordinate system used
was NAD83, Zone 20, which is
ASX: ABR | albrightmetals.com 16
Criteria JORC Code explanation Commentary
Specification of the grid
system used.
Quality and adequacy of
topographic control.
a Universal Transverse
Mercator (UTM) grid.
High quality LIDAR is available
from the Government of New
Brunswick GIS datasets for
topographic control.
Data spacing
and distribution
Data spacing for reporting of
Exploration Results.
Whether the data spacing
and distribution is sufficient
to establish the degree of
geological and grade
continuity appropriate for
the Mineral Resource and
Ore Reserve estimation
procedure(s) and
classifications applied.
Whether sample
compositing has been
applied.
Drill spacing at the Vail Road
Gold deposit ranges from
sections spaced 12.5 – 25m
apart, with collars spaced
between 12.5 – 25m on section
for the Main Zone. The Parallel
Zone is broadly at 50m spaced
drill sections, with three holes
in this program infilling to 25m
spacing. The Middle Zone is
drilled at spacing ranging from
12.5m to 25m. Some pairs of
holes are closer in all zones
where twin holes have been
drilled.
Data spacing is adequate for
geological modelling to
support a mineral resource
estimation, and collection of
structural data during this
campaign validates the
existing interpretation of the
zone continuity at the deposit.
Samples have been calculated
as intercepts greater than 1 g/t
Au with no minimum width
(although minimum sample
length is 0.3m) in this release,
as a weighted average from
primary assay samples.
Orientation of
data in relation
to geological
structure
Whether the orientation of
sampling achieves unbiased
sampling of possible
structures and the extent to
which this is known,
considering the deposit type.
If the relationship between
the drilling orientation and
the orientation of key
mineralised structures is
considered to have
The deposit has a series of
lodes that strike about
northeast, dipping steeply to
moderately to northwest.
Specifically, the Parallel Zone
dips 72 degrees towards 325
(NW), the Middle Zone dips 72
degrees towards 345 degrees
(N-NW) and the Main Zone
dips 81 degrees towards 310
degrees (NW).
ASX: ABR | albrightmetals.com 17
Criteria JORC Code explanation Commentary
introduced a sampling bias,
this should be assessed and
reported if material.
Hole directions in the 2025
program are typically as close
to perpendicular to the
mineralisation as possible, with
exception of some peripheral
holes that were designed to
test structural controls on
mineralisation boundaries, or
one vertical hole designed for
a future water monitoring bore
in addition to geological
information. Hole VR-25-76 is
drilled at a 140-degree azimuth
(typically 117 degrees for other
holes) designed to intersect
the Middle Zone at an azimuth
more perpendicular to the
345-degree strike of the lode.
Drill orientations with respect
to the mineralisation
orientations is not considered
to have introduced a sampling
bias.
Sample security The measures taken to
ensure sample security.
Diamond core was securely
stored at the Sussex Core
Facility, property of the
Government of New
Brunswick - Natural Resources.
The core remained within
custody of the geological team
supervising and processing
the core at the Sussex Core
Facility after being collected
from the rig each day.
Samples were zip tied into
plastic bags, then zip tied into
polyweave (rice) bags, then
delivered by the geological
team to the lab. Samples
remained within custody of
the Canadian geological team
supervising and processing
the drilling at all times.
Audits or
reviews
The results of any audits or
reviews of sampling
techniques and data.
No audits or reviews of
sampling techniques has been
completed.
ASX: ABR | albrightmetals.com 18
Section 2 Reporting of Exploration Results (Criteria listed in the preceding section
also apply to this section.)
Criteria JORC Code explanation Commentary
Mineral
tenement and
land tenure
status
Type, reference
name/number, location and
ownership including
agreements or material
issues with third parties such
as joint ventures,
partnerships, overriding
royalties, native title interests,
historical sites, wilderness or
national park and
environmental settings.
The security of the tenure
held at the time of reporting
along with any known
impediments to obtaining a
licence to operate in the area.
The relevant claim (7616) is
100% owned by the Globex
Mining Enterprises Inc.
Albright Metals have an Option
Agreement to earn ownership
of the Mineral Claim.
At the time of reporting, there
are no known impediments to
obtaining a licence to operate
in the area.
Exploration
done by other
parties
Acknowledgment and
appraisal of exploration by
other parties.
At Vail Road Gold Deposit,
numerous workers (Noranda
Exploration Company Limited
(in JV with Forsters); Rockport
Mining Limited; Globex Mining
Enterprises Inc.) completed
diamond core drilling,
trenching, surface soil
sampling and prospecting
with rock chip samples
between 1994 and 2017.
Induced Polarisation and
Aerial Magnetics surveys were
completed over the entire
Mineral Claim area,
encompassing both Bond
Road antimony prospect and
Vail Road Gold Deposit, in
addition to other prospects
shown in Figure 1 that is the
Project prospect map.
Aerial magnetics was flown by
Globex Mining Enterprises Inc.
via Novatem Airborne
Geophysics during 2022; this
data was collected using a
helicopter-borne system using
two laser optically pumped
sensors providing 1,000
measurements per second
ASX: ABR | albrightmetals.com 19
Criteria JORC Code explanation Commentary
(1,000 Hz) mounted on the
front of a Guimbal G2 light
helicopter. The survey covered
the 7616 Claim Area, being
32.8km2
. The flight line spacing
was 25m and the control line
spacing was 250m. Line
orientation was North (0
degrees) and control line
orientation was East (90
degrees). The sensor height
above the ground was drape
20m.
Geology Deposit type, geological
setting and style of
mineralisation.
The project is located in south-
central New Brunswick, within
the Appalachian Orogen. It lies
near the boundary between
the Cambro-Ordovician
Annidale Group (to the
northwest), and the Siluro-
Devonian Mascarene Cover
Sequence (to the southeast),
with the Taylor Brook Fault
separating the major tectonic
units, and the sub-parallel
Albright Brook Fault within the
Annidale Group.
Vail Road Gold Deposit is
within basaltic flows and pillow
basalts and minor sedimentary
volcaniclastic units with three
quartz vein zones that contain
the gold mineralisation in the
Grant Brook Formation.
Previous interpretations of the
veining are that it is a folded
v